The Nevada County Transportation Commission has decided not to continue the Highway 49-LaBarr Meadows Project. Caltrans went 840-thousand dollars over budget and is seeking more money from the state Transportation Commission. The Nevada County Transportation Commission had a special meeting this morning (Friday)…
That’s N-C-T-C Executive Director Dan Landon. The project, which widened Highway 49, was almost complete, but Landon says there were three elements left undone…
And the third is the striping, which will be done with reflective paint instead of the longer-lasting thermal plastic striping. The decision by the N-C-T-C doesn’t necessarily kill the project. Caltrans Deputy Director Tom Brannon says that’s still undetermined…
The commission voted 6-1 against additional funding. Commission Chair Larry Jostes cast the dissenting vote.