Brunswick Road to Open Ahead of Schedule

It’s a pleasant surprise from the Nevada County Road Department. The Brunswick Road emergency project will be done early…

Listen to Joshua Pack 1

Principal Civil Engineer Joshua Pack says the road has been repaired, they dug up, removed, and replaced four thousand cubic yards of road fill, and installed underground drainage pipes. Pack says the underground drains they put in before they started the main road work, really worked…

Listen to Joshua Pack 2

Part of the roadway near the East Bennett-Greenhorn Road intersection gave way because of saturation during last winter’s storms. Pack says paving is being done today, and then they’ll do the striping, and then have the roadway open by this weekend. The original completion date was supposed to be August 11.

–gf

KNCO Web Comments Guidelines

  1. Keep it clean. Comments with inappropriate language, no matter how cleverly spelled or decorated will not be posted.
  2. Comments on the way the story was written or misspelled words will be passed on to the story authors and not posted.
  3. Please use your real name. Anonymous comments or comments posted using a fake name or web handle may not be posted.
  4. Please use your real email address so we can contact you.
  5. No flaming. Any comments that are primarily of a name calling finger pointing nature may not be posted.
  6. The comment section is not a right it is a privilege. KNCO retains all rights as to what is posted on its website.

Leave A Comment

*

*

* captcha