What’s considered the most soild construction cost range, so far, for the Centennial Dam project has been released. Nevada Irrigation District General Manager, Rem Scherzinger, says the latest studies have a range of $217 million to $307 million. But he says it will take a while longer to come up with a specific grand total, also including other expenses….
click to listen to Rem Scherzinger
Scherzinger says funding options include…
click to listen to Rem Scherzinger
Scherzinger says the information will also help complete the financial feasibility report. It’s hoped a final cost will be out with the environmental impact report in the fall. He says construction of the dam will likely take about 2 and a half years. And he’s still optimistic that work can begin in time for the 2021 centennial of the district.